In a scheduling set involving four tasks A, B, C, and D, if task A must be completed before task B, and task C cannot start until task D is finished, which of the following sequences is valid?

Practice Questions

1 question
Q1
In a scheduling set involving four tasks A, B, C, and D, if task A must be completed before task B, and task C cannot start until task D is finished, which of the following sequences is valid?
  1. A, B, C, D
  2. D, C, A, B
  3. B, A, D, C
  4. C, D, A, B

Questions & Step-by-step Solutions

1 item
Q
Q: In a scheduling set involving four tasks A, B, C, and D, if task A must be completed before task B, and task C cannot start until task D is finished, which of the following sequences is valid?
Solution: The only valid sequence is D, C, A, B, as it respects the constraints given.
Steps: 6