In a scheduling set, if task J can only start after task K is completed, which of the following is a valid conclusion?

Practice Questions

1 question
Q1
In a scheduling set, if task J can only start after task K is completed, which of the following is a valid conclusion?
  1. K can start after J
  2. J can start at any time
  3. K must be completed before J
  4. J is independent of K

Questions & Step-by-step Solutions

1 item
Q
Q: In a scheduling set, if task J can only start after task K is completed, which of the following is a valid conclusion?
Solution: Task J can only start after K is completed, making this conclusion valid.
Steps: 4