In a scheduling set, if task E can only start after task D and task D can only start after task C, which of the following is a valid order?

Practice Questions

1 question
Q1
In a scheduling set, if task E can only start after task D and task D can only start after task C, which of the following is a valid order?
  1. C, D, E, A
  2. D, C, E, A
  3. E, D, C, A
  4. A, C, D, E

Questions & Step-by-step Solutions

1 item
Q
Q: In a scheduling set, if task E can only start after task D and task D can only start after task C, which of the following is a valid order?
Solution: C, D, E, A is valid as E starts after D and D starts after C.
Steps: 5