In a scheduling scenario, if task F is dependent on tasks G and H, which of the following is a correct statement?

Practice Questions

1 question
Q1
In a scheduling scenario, if task F is dependent on tasks G and H, which of the following is a correct statement?
  1. F can start before G and H
  2. G and H must be completed before F
  3. F can be completed at any time
  4. H is independent of F

Questions & Step-by-step Solutions

1 item
Q
Q: In a scheduling scenario, if task F is dependent on tasks G and H, which of the following is a correct statement?
Solution: Task F can only start after both G and H are completed, making this statement correct.