In a scheduling scenario, if task B is dependent on both tasks A and C being completed, which of the following sequences is valid?

Practice Questions

1 question
Q1
In a scheduling scenario, if task B is dependent on both tasks A and C being completed, which of the following sequences is valid?
  1. C, A, B, D
  2. A, B, C, D
  3. B, A, C, D
  4. A, C, D, B

Questions & Step-by-step Solutions

1 item
Q
Q: In a scheduling scenario, if task B is dependent on both tasks A and C being completed, which of the following sequences is valid?
Solution: C, A, B, D is valid as B starts after both A and C.