In a project with tasks A, B, C, and D, if task C can only start after both A and B are completed, which of the following is a valid sequence?

Practice Questions

1 question
Q1
In a project with tasks A, B, C, and D, if task C can only start after both A and B are completed, which of the following is a valid sequence?
  1. A, B, C, D
  2. B, A, D, C
  3. C, A, B, D
  4. D, C, A, B

Questions & Step-by-step Solutions

1 item
Q
Q: In a project with tasks A, B, C, and D, if task C can only start after both A and B are completed, which of the following is a valid sequence?
Solution: A, B, C, D is valid as C starts after both A and B.
Steps: 7