If task A must be completed before task B, and task B must be completed before task C, which of the following is a correct sequence?

Practice Questions

1 question
Q1
If task A must be completed before task B, and task B must be completed before task C, which of the following is a correct sequence?
  1. C, B, A
  2. B, A, C
  3. A, C, B
  4. A, B, C

Questions & Step-by-step Solutions

1 item
Q
Q: If task A must be completed before task B, and task B must be completed before task C, which of the following is a correct sequence?
Solution: A, B, C is the correct sequence as it respects the order of dependencies.