Question: If a team of 6 people can finish a project in 15 days, how many days will it take for 3 people to finish the same project?
Options:
Correct Answer: 45
Solution:
The work done is constant. If 6 people take 15 days, then 3 people will take 15 * (6/3) = 30 days.