Question: A worker can complete a job in 10 days. How much of the job can he complete in 3 days?
Options:
1/10
1/5
3/10
1/3
Correct Answer: 3/10
Solution:
Work done in 1 day = 1/10. Work done in 3 days = 3 * (1/10) = 3/10.
A worker can complete a job in 10 days. How much of the job can he complete in 3
Practice Questions
Q1
A worker can complete a job in 10 days. How much of the job can he complete in 3 days?
1/10
1/5
3/10
1/3
Questions & Step-by-Step Solutions
A worker can complete a job in 10 days. How much of the job can he complete in 3 days?
Step 1: Understand that the worker can finish the entire job in 10 days.
Step 2: Calculate how much of the job the worker completes in 1 day. This is done by taking 1 job and dividing it by 10 days, which gives us 1/10 of the job per day.
Step 3: Now, we want to find out how much of the job the worker can complete in 3 days.
Step 4: To find the work done in 3 days, multiply the work done in 1 day (1/10) by 3 days. This is 3 * (1/10).
Step 5: Calculate the result of 3 * (1/10), which equals 3/10. This means the worker can complete 3/10 of the job in 3 days.
Work Rate – Understanding how to calculate work done based on a worker's rate of completing a job.
Fraction Multiplication – Applying multiplication of fractions to determine the portion of work completed over a period.