Question: A project requires 120 hours of work. If 3 workers are assigned, how long will it take to complete the project?

Options:

  1. 30 hours
  2. 40 hours
  3. 50 hours
  4. 60 hours

Correct Answer: 40 hours

Solution:

Total man-hours = 120. For 3 workers, time = 120/3 = 40 hours.

A project requires 120 hours of work. If 3 workers are assigned, how long will i

Practice Questions

Q1
A project requires 120 hours of work. If 3 workers are assigned, how long will it take to complete the project?
  1. 30 hours
  2. 40 hours
  3. 50 hours
  4. 60 hours

Questions & Step-by-Step Solutions

A project requires 120 hours of work. If 3 workers are assigned, how long will it take to complete the project?
  • Work Rate – Understanding how to calculate the time required to complete a project based on the number of workers and total work hours.