Question: If 4 workers can finish a job in 16 days, how many days will 8 workers take to finish the same job?

Options:

  1. 8 days
  2. 10 days
  3. 12 days
  4. 14 days

Correct Answer: 8 days

Solution:

Work = 4 workers × 16 days = 64 man-days. For 8 workers, days = 64/8 = 8 days.

If 4 workers can finish a job in 16 days, how many days will 8 workers take to f

Practice Questions

Q1
If 4 workers can finish a job in 16 days, how many days will 8 workers take to finish the same job?
  1. 8 days
  2. 10 days
  3. 12 days
  4. 14 days

Questions & Step-by-Step Solutions

If 4 workers can finish a job in 16 days, how many days will 8 workers take to finish the same job?
  • Step 1: Understand that 4 workers can finish a job in 16 days.
  • Step 2: Calculate the total amount of work done in 'man-days'. This is done by multiplying the number of workers by the number of days: 4 workers × 16 days = 64 man-days.
  • Step 3: Now, we want to find out how many days it will take for 8 workers to finish the same job.
  • Step 4: To find the number of days for 8 workers, divide the total work (64 man-days) by the number of workers (8): 64 man-days ÷ 8 workers = 8 days.
  • Step 5: Therefore, 8 workers will take 8 days to finish the job.
  • Work Rate – The concept of work rate involves understanding how the number of workers and the time taken to complete a job are inversely related.
  • Man-Days – Man-days is a unit of measure that combines the number of workers and the number of days they work to complete a task.