If 4 workers can finish a job in 16 days, how many days will 8 workers take to f

Practice Questions

Q1
If 4 workers can finish a job in 16 days, how many days will 8 workers take to finish the same job?
  1. 8 days
  2. 10 days
  3. 12 days
  4. 14 days

Questions & Step-by-Step Solutions

If 4 workers can finish a job in 16 days, how many days will 8 workers take to finish the same job?