Question: If A can complete a task in 10 days and B can do it in 15 days, how much work can they complete together in 1 day?
Options:
Correct Answer: 1/6
Solution:
A\'s rate = 1/10, B\'s rate = 1/15. Combined rate = 1/10 + 1/15 = 1/6.