If A can complete a work in 18 days and B can complete it in 27 days, how long will it take for them to finish the work if A works for 6 days and then B works for 6 days?
  1. 10 days
  2. 12 days
  3. 14 days
  4. 16 days

Questions & Step-by-Step Solutions

If A can complete a work in 18 days and B can complete it in 27 days, how long will it take for them to finish the work if A works for 6 days and then B works for 6 days?