If A can complete a work in 18 days and B can complete it in 27 days, how long w
Practice Questions
Q1
If A can complete a work in 18 days and B can complete it in 27 days, how long will it take for them to finish the work if A works for 6 days and then B works for 6 days?
10 days
12 days
14 days
16 days
Questions & Step-by-Step Solutions
If A can complete a work in 18 days and B can complete it in 27 days, how long will it take for them to finish the work if A works for 6 days and then B works for 6 days?