A can complete a work in 16 days, B in 24 days, and C in 32 days. If they all work together, how long will it take to complete the work?
  1. 6 days
  2. 8 days
  3. 10 days
  4. 12 days

Questions & Step-by-Step Solutions

A can complete a work in 16 days, B in 24 days, and C in 32 days. If they all work together, how long will it take to complete the work?