If 6 workers can complete a task in 15 days, how many workers are needed to comp

Practice Questions

Q1
If 6 workers can complete a task in 15 days, how many workers are needed to complete the task in 10 days?
  1. 8 workers
  2. 9 workers
  3. 10 workers
  4. 12 workers

Questions & Step-by-Step Solutions

If 6 workers can complete a task in 15 days, how many workers are needed to complete the task in 10 days?
No concepts available.
Soulshift Feedback ×

On a scale of 0–10, how likely are you to recommend The Soulshift Academy?

Not likely Very likely