Question: If 6 workers can complete a task in 15 days, how many workers are needed to complete the task in 10 days?
Options:
Correct Answer: 10 workers
Solution:
Total work = 6 workers * 15 days = 90 man-days. To complete in 10 days, needed workers = 90/10 = 9 workers.