Question: If a man can finish a work in 25 days, how long will it take for him to finish 40% of the work?

Options:

  1. 10 days
  2. 12 days
  3. 15 days
  4. 20 days

Correct Answer: 12 days

Solution:

40% of the work = 0.4 * 25 days = 10 days.

If a man can finish a work in 25 days, how long will it take for him to finish 4

Practice Questions

Q1
If a man can finish a work in 25 days, how long will it take for him to finish 40% of the work?
  1. 10 days
  2. 12 days
  3. 15 days
  4. 20 days

Questions & Step-by-Step Solutions

If a man can finish a work in 25 days, how long will it take for him to finish 40% of the work?
  • Step 1: Understand that the man can finish the entire work in 25 days.
  • Step 2: Calculate 40% of the work. This means we need to find 40% of 25 days.
  • Step 3: Convert 40% to a decimal. 40% is the same as 0.4.
  • Step 4: Multiply the total days (25) by 0.4 to find out how many days it takes to finish 40% of the work.
  • Step 5: Perform the calculation: 0.4 * 25 = 10 days.
  • Step 6: Conclude that it will take the man 10 days to finish 40% of the work.
  • Work and Time Calculation – Understanding the relationship between the total time to complete a task and the fraction of the task completed.