If 6 workers can finish a job in 15 days, how many workers are needed to finish

Practice Questions

Q1
If 6 workers can finish a job in 15 days, how many workers are needed to finish the job in 10 days?
  1. 8 workers
  2. 9 workers
  3. 10 workers
  4. 12 workers

Questions & Step-by-Step Solutions

If 6 workers can finish a job in 15 days, how many workers are needed to finish the job in 10 days?