A task requires 60 hours of work. If 3 workers are assigned to it, how long will

Practice Questions

Q1
A task requires 60 hours of work. If 3 workers are assigned to it, how long will it take them to complete the task?
  1. 15 hours
  2. 20 hours
  3. 25 hours
  4. 30 hours