A civil servant has to complete a project in 120 days. If they have already spent 30 days, what percentage of the time is left to complete the project?
  1. 75%
  2. 70%
  3. 80%
  4. 60%

Questions & Step-by-Step Solutions

A civil servant has to complete a project in 120 days. If they have already spent 30 days, what percentage of the time is left to complete the project?