Question: A civil servant has to complete a project in 120 days. If they have already spent 30 days, what percentage of the time is left to complete the project?
Options:
Correct Answer: 75%
Solution:
Time left = Total time - Time spent = 120 - 30 = 90 days. Percentage left = (90/120) x 100 = 75%.