Question: If a public service project is expected to take 18 months and is currently 2 months in, what percentage of the project time has elapsed?

Options:

  1. 10%
  2. 11%
  3. 12%
  4. 13%

Correct Answer: 11%

Solution:

Percentage elapsed = (2 months / 18 months) * 100 = 11.11%, approximately 11%.

If a public service project is expected to take 18 months and is currently 2 mon

Practice Questions

Q1
If a public service project is expected to take 18 months and is currently 2 months in, what percentage of the project time has elapsed?
  1. 10%
  2. 11%
  3. 12%
  4. 13%

Questions & Step-by-Step Solutions

If a public service project is expected to take 18 months and is currently 2 months in, what percentage of the project time has elapsed?
  • Step 1: Identify the total time expected for the project, which is 18 months.
  • Step 2: Identify the time that has already passed, which is 2 months.
  • Step 3: Divide the time that has passed (2 months) by the total time (18 months).
  • Step 4: Calculate the result of the division: 2 / 18 = 0.1111.
  • Step 5: To find the percentage, multiply the result by 100: 0.1111 * 100 = 11.11.
  • Step 6: Round the percentage to the nearest whole number, which is approximately 11%.
  • Percentage Calculation – Understanding how to calculate the percentage of a part relative to a whole.
  • Time Management in Projects – Recognizing the importance of tracking elapsed time in project management.