Question: If a project is planned to take 40 days with 5 workers, how many days will it take if the number of workers is increased to 10?
Options:
Correct Answer: 20
Solution:
The total work is 5 * 40 = 200 worker-days. With 10 workers, it will take 200 / 10 = 20 days.