Q1
If a project is planned to take 40 days with 5 workers, how many days will it take if the number of workers is increased to 10?
  1. 20
  2. 25
  3. 30
  4. 35

Questions & Step-by-Step Solutions

If a project is planned to take 40 days with 5 workers, how many days will it take if the number of workers is increased to 10?