Question: A team of 5 people can complete a task in 15 days. How many days will it take for 10 people to complete the same task?
Options:
Correct Answer: 7.5
Solution:
The total work is 5 * 15 = 75 person-days. With 10 people, it will take 75 / 10 = 7.5 days.