Question: If 3 workers can complete a task in 12 days, how many days will it take for 6 workers to complete the same task?
Options:
Correct Answer: 6 days
Solution:
Work done = 3 workers × 12 days = 36 worker-days. For 6 workers, days = 36 worker-days / 6 workers = 6 days.