Question: A and B can complete a work in 12 days and 18 days respectively. If they work together, how long will it take them to complete the work?
Options:
Correct Answer: 8 days
Solution:
A\'s work rate = 1/12, B\'s work rate = 1/18. Together, they work at (1/12 + 1/18) = 5/36. Time taken = 36/5 = 7.2 days.