Question: If 6 people can finish a job in 8 days, how many people are needed to finish the job in 4 days?
Options:
Correct Answer: 12 people
Solution:
6 people take 8 days, so total work = 6 * 8 = 48 person-days. To finish in 4 days, needed people = 48 / 4 = 12 people.