Question: If 8 people can complete a project in 12 days, how many people are needed to complete the project in 6 days?
Options:
Correct Answer: 16 people
Solution:
If 8 people take 12 days, then the total work is 8 * 12 = 96 person-days. To complete in 6 days, needed people = 96 / 6 = 16 people.