Question: A can do a work in 12 days, B can do it in 18 days, and C can do it in 24 days. If they work together, how long will they take to complete the work?
Options:
Correct Answer: 6
Solution:
A\'s rate = 1/12, B\'s rate = 1/18, C\'s rate = 1/24. Combined rate = 1/12 + 1/18 + 1/24 = 1/4. They will complete the work in 4 days.