Question: If 6 workers can build a wall in 8 days, how many workers are needed to build the wall in 4 days?
Options:
Correct Answer: 12 workers
Solution:
Work = 6 workers * 8 days = 48 worker-days. To finish in 4 days, needed = 48 worker-days / 4 days = 12 workers.