Question: If 5 workers can complete a task in 12 days, how many days will it take for 10 workers to complete the same task?
Options:
Correct Answer: 6
Solution:
Work done by 5 workers in 12 days = 1 work unit. Work done by 1 worker in 60 days = 1/60 work unit/day. For 10 workers, rate = 10/60 = 1/6 work unit/day. Time = 1/(1/6) = 6 days.