Question: If 4 men can complete a work in 10 days, how many men are required to complete the same work in 5 days?
Options:
Correct Answer: 8
Solution:
Work done by 4 men in 10 days = 1 work unit. Work done by 1 man in 40 days = 1/40 work unit/day. To complete in 5 days, required rate = 1/5 work unit/day. Number of men = 1/(1/40) * 5 = 8.