Question: If 8 people can finish a project in 12 days, how many people are needed to finish the project in 6 days?
Options:
Correct Answer: 16 people
Solution:
Work done = People * Days. 8 * 12 = 96 person-days. To finish in 6 days, needed = 96 / 6 = 16 people.