Question: If 12 workers can complete a task in 10 days, how many days will it take for 6 workers to complete the same task?
Options:
Correct Answer: 30 days
Solution:
Work done = Workers × Days. 12 workers × 10 days = 120 worker-days. 6 workers will take 120 / 6 = 20 days.