Question: If 12 workers can complete a task in 15 days, how many days will it take for 6 workers to complete the same task?
Options:
Correct Answer: 45 days
Solution:
Work done = Workers × Days. Total work = 12 × 15 = 180. For 6 workers, Days = 180 / 6 = 30 days.