Question: A can do a work in 20 days, B can do it in 30 days, and C can do it in 60 days. If all three work together, how long will they take to complete the work?
Options:
Correct Answer: 5
Solution:
A\'s rate = 1/20, B\'s rate = 1/30, C\'s rate = 1/60. Combined rate = 1/20 + 1/30 + 1/60 = 1/10. They will complete the work in 10 days.