Question: A can complete a work in 10 days, while B can complete the same work in 15 days. If both work together, how many days will they take to complete the work?
Options:
Correct Answer: 6
Solution:
A\'s work rate = 1/10, B\'s work rate = 1/15. Combined rate = 1/10 + 1/15 = 1/6. They will complete the work in 6 days.