Question: A worker can complete a job in 10 days. How much of the job will he complete in 3 days?
Options:
1/3
1/4
1/5
1/2
Correct Answer: 1/3
Solution:
Work done in 1 day = 1/10. Work done in 3 days = 3 * (1/10) = 3/10.
A worker can complete a job in 10 days. How much of the job will he complete in
Practice Questions
Q1
A worker can complete a job in 10 days. How much of the job will he complete in 3 days?
1/3
1/4
1/5
1/2
Questions & Step-by-Step Solutions
A worker can complete a job in 10 days. How much of the job will he complete in 3 days?
Step 1: Understand that the worker can finish the entire job in 10 days.
Step 2: Calculate how much of the job the worker completes in 1 day. This is done by taking 1 job and dividing it by 10 days, which gives us 1/10 of the job per day.
Step 3: Now, to find out how much of the job is completed in 3 days, multiply the amount of work done in 1 day (1/10) by 3 days.
Step 4: Perform the multiplication: 3 * (1/10) = 3/10.
Step 5: Conclude that in 3 days, the worker will complete 3/10 of the job.
Work Rate – Understanding how to calculate work done based on a worker's rate of completing a job.
Proportionality – Applying proportional reasoning to determine the fraction of work completed over a given time.