Question: A can complete a task in 18 days, B can complete it in 27 days. How long will they take to complete the task together?
Options:
Correct Answer: 9 days
Solution:
A\'s rate = 1/18, B\'s rate = 1/27. Combined rate = 1/18 + 1/27 = 1/10. They will finish the task in 10 days.