In a project management context, which of the following best describes 'resource

Practice Questions

Q1
In a project management context, which of the following best describes 'resource leveling'?
  1. Distributing resources evenly across all tasks.
  2. Adjusting the start and finish dates of tasks to balance resource usage.
  3. Allocating more resources to critical tasks only.
  4. Reducing the overall project scope.

Questions & Step-by-Step Solutions

In a project management context, which of the following best describes 'resource leveling'?
  • Step 1: Understand what 'resource leveling' means in project management.
  • Step 2: Recognize that it is about managing resources effectively.
  • Step 3: Identify that resource leveling adjusts task schedules.
  • Step 4: Realize the goal is to balance how resources are used across tasks.
  • Step 5: Conclude that the correct answer is the one that describes this adjustment and balance.