Question: In a project management context, which of the following best describes \'resource leveling\'?
Options:
Correct Answer: Adjusting the start and finish dates of tasks to balance resource usage.
Solution:
Resource leveling involves adjusting task schedules to balance resource usage, making option 1 the correct answer.