Question: If task E can only start after tasks A and D are completed, which of the following is a correct statement regarding the scheduling of these tasks?

Options:

  1. E can start before A and D.
  2. E can start after A or D.
  3. E can start only after both A and D are completed.
  4. E can start at any time.

Correct Answer: E can start only after both A and D are completed.

Solution:

E can only start after both A and D are completed, as per the given condition.

If task E can only start after tasks A and D are completed, which of the followi

Practice Questions

Q1
If task E can only start after tasks A and D are completed, which of the following is a correct statement regarding the scheduling of these tasks?
  1. E can start before A and D.
  2. E can start after A or D.
  3. E can start only after both A and D are completed.
  4. E can start at any time.

Questions & Step-by-Step Solutions

If task E can only start after tasks A and D are completed, which of the following is a correct statement regarding the scheduling of these tasks?
  • Step 1: Identify the tasks involved: A, D, and E.
  • Step 2: Understand the condition: Task E can only start after tasks A and D are completed.
  • Step 3: Recognize that both A and D must be finished before E can begin.
  • Step 4: Conclude that E's start time is dependent on the completion of A and D.
  • Task Dependency – Understanding that certain tasks cannot begin until prerequisite tasks are completed.
  • Scheduling – The process of planning the order and timing of tasks based on their dependencies.