Question: In a scheduling scenario, if task A takes 2 hours, task B takes 3 hours, and task C takes 1 hour, which of the following combinations allows for the earliest completion of all tasks if A must be done before B?

Options:

  1. A, B, C
  2. C, A, B
  3. B, A, C
  4. A, C, B

Correct Answer: C, A, B

Solution:

The combination C, A, B allows for the earliest completion since C takes the least time and can be done first.

In a scheduling scenario, if task A takes 2 hours, task B takes 3 hours, and tas

Practice Questions

Q1
In a scheduling scenario, if task A takes 2 hours, task B takes 3 hours, and task C takes 1 hour, which of the following combinations allows for the earliest completion of all tasks if A must be done before B?
  1. A, B, C
  2. C, A, B
  3. B, A, C
  4. A, C, B

Questions & Step-by-Step Solutions

In a scheduling scenario, if task A takes 2 hours, task B takes 3 hours, and task C takes 1 hour, which of the following combinations allows for the earliest completion of all tasks if A must be done before B?
  • Step 1: Identify the tasks and their durations: Task A takes 2 hours, Task B takes 3 hours, and Task C takes 1 hour.
  • Step 2: Note the requirement that Task A must be completed before Task B.
  • Step 3: Consider the possible combinations of tasks while keeping the requirement in mind.
  • Step 4: Evaluate the combination C, A, B: First do Task C (1 hour), then Task A (2 hours), and finally Task B (3 hours).
  • Step 5: Calculate the total time for the combination C, A, B: 1 hour (C) + 2 hours (A) + 3 hours (B) = 6 hours.
  • Step 6: Check other combinations like A, C, B or A, B, C to see if they finish earlier, but they will take longer due to the requirement of A before B.
  • Step 7: Conclude that the combination C, A, B allows for the earliest completion of all tasks.
  • Task Scheduling – Understanding the order and duration of tasks to determine the earliest completion time.
  • Dependency Management – Recognizing task dependencies, such as task A needing to be completed before task B.