Question: If a worker can complete a task in 10 hours, how much of the task can he complete in 2.5 hours?

Options:

  1. 0.2
  2. 0.25
  3. 0.3
  4. 0.5

Correct Answer: 0.25

Solution:

In 2.5 hours, the worker completes (2.5/10) = 0.25 of the task.

If a worker can complete a task in 10 hours, how much of the task can he complet

Practice Questions

Q1
If a worker can complete a task in 10 hours, how much of the task can he complete in 2.5 hours?
  1. 0.2
  2. 0.25
  3. 0.3
  4. 0.5

Questions & Step-by-Step Solutions

If a worker can complete a task in 10 hours, how much of the task can he complete in 2.5 hours?
  • Step 1: Understand that the worker can complete the entire task in 10 hours.
  • Step 2: Determine how much of the task the worker can complete in 1 hour. This is done by dividing 1 by 10, which equals 0.1. So, in 1 hour, the worker completes 0.1 of the task.
  • Step 3: Now, find out how much of the task the worker can complete in 2.5 hours. Multiply the amount completed in 1 hour (0.1) by 2.5. This gives you 0.1 * 2.5 = 0.25.
  • Step 4: Conclude that in 2.5 hours, the worker completes 0.25 of the task.
  • Work Rate – Understanding how to calculate the portion of work completed based on time and total time required.