Question: In a scheduling scenario, if task E can only start after task D is completed, which of the following is a valid implication?

Options:

  1. D can start after E
  2. E can start before D
  3. D must be completed before E
  4. E and D can start simultaneously

Correct Answer: D must be completed before E

Solution:

E can only start after D is completed, making the implication true.

In a scheduling scenario, if task E can only start after task D is completed, wh

Practice Questions

Q1
In a scheduling scenario, if task E can only start after task D is completed, which of the following is a valid implication?
  1. D can start after E
  2. E can start before D
  3. D must be completed before E
  4. E and D can start simultaneously

Questions & Step-by-Step Solutions

In a scheduling scenario, if task E can only start after task D is completed, which of the following is a valid implication?
  • Step 1: Identify the tasks involved. We have task D and task E.
  • Step 2: Understand the relationship between the tasks. Task E can only start after task D is completed.
  • Step 3: Recognize what this means. If task D is not completed, task E cannot start.
  • Step 4: Conclude the implication. Since E can only start after D is completed, this statement is true.
  • Task Dependency – Understanding that one task cannot begin until another task is completed.