Question: If task F must be completed before task G and task H can only start after task F, which of the following is true?

Options:

  1. G can start before F.
  2. H can start before G.
  3. F must be completed before both G and H.
  4. G must be completed before F.

Correct Answer: F must be completed before both G and H.

Solution:

F must be completed before both G and H according to the given constraints.

If task F must be completed before task G and task H can only start after task F

Practice Questions

Q1
If task F must be completed before task G and task H can only start after task F, which of the following is true?
  1. G can start before F.
  2. H can start before G.
  3. F must be completed before both G and H.
  4. G must be completed before F.

Questions & Step-by-Step Solutions

If task F must be completed before task G and task H can only start after task F, which of the following is true?
  • Step 1: Identify the tasks involved: F, G, and H.
  • Step 2: Understand the constraints: Task F must be completed before task G can start.
  • Step 3: Note that task H can only start after task F is completed.
  • Step 4: Since task G cannot start until F is done, and H also cannot start until F is done, it means F must be completed before both G and H.
  • Task Dependency – Understanding the order in which tasks must be completed based on given constraints.
  • Logical Reasoning – Applying logical reasoning to deduce the implications of task dependencies.