Question: A group of students can complete a project in 12 days. If 4 more students join, the project can be completed in 8 days. How many students were initially in the group? (2023)
Options:
Correct Answer: 8
Exam Year: 2023
Solution:
Let the initial number of students be x. The work done is constant, so x * 12 = (x + 4) * 8. Solving gives x = 8.