Question: If 5 workers can complete a task in 10 days, how many days will it take for 10 workers to complete the same task?
Options:
Correct Answer: 5 days
Solution:
Work done = Workers * Days. Total work = 5 * 10 = 50 worker-days. For 10 workers, Days = Total work / Workers = 50 / 10 = 5 days.