Question: If tasks P, Q, R, and S are scheduled such that P must be completed before Q, and R must be completed before S, which of the following is a possible order?
Options:
Correct Answer: P, Q, R, S
Solution:
The order P, Q, R, S respects the constraints that P is before Q and R is before S.