In a project involving tasks A, B, C, and D, if task D can only start after task

Practice Questions

Q1
In a project involving tasks A, B, C, and D, if task D can only start after task B is completed, which of the following is a valid conclusion?
  1. B must be completed before D
  2. D can start before B
  3. A can start after D
  4. C must be completed before B

Questions & Step-by-Step Solutions

In a project involving tasks A, B, C, and D, if task D can only start after task B is completed, which of the following is a valid conclusion?
  • Step 1: Identify the tasks involved in the project: A, B, C, and D.
  • Step 2: Understand the condition given: Task D can only start after task B is completed.
  • Step 3: Recognize what this condition means: It means that B must finish before D can begin.
  • Step 4: Conclude that since D depends on B, B must be completed first for D to start.