If task D must be completed before task E and task F can only start after task D

Practice Questions

Q1
If task D must be completed before task E and task F can only start after task D, which of the following is true?
  1. E can start before D.
  2. F can start before E.
  3. D must be completed before both E and F.
  4. E must be completed before D.

Questions & Step-by-Step Solutions

If task D must be completed before task E and task F can only start after task D, which of the following is true?
  • Step 1: Identify the tasks involved: D, E, and F.
  • Step 2: Understand the conditions: Task D must be completed before task E can start.
  • Step 3: Note that task F can only start after task D is completed.
  • Step 4: Since task E depends on task D, and task F also depends on task D, it means D must be completed before both E and F.