In a scheduling scenario, if task F must be completed before task G and task H can be done at any time, which of the following is true?

Practice Questions

1 question
Q1
In a scheduling scenario, if task F must be completed before task G and task H can be done at any time, which of the following is true?
  1. H must be done before F.
  2. G can start before F.
  3. F must be done before H.
  4. G cannot start until F is done.

Questions & Step-by-step Solutions

1 item
Q
Q: In a scheduling scenario, if task F must be completed before task G and task H can be done at any time, which of the following is true?
Solution: G cannot start until F is completed, as per the given condition.
Steps: 4

Related Questions

Soulshift Feedback ×

On a scale of 0–10, how likely are you to recommend The Soulshift Academy?

Not likely Very likely