Question: In a project with tasks P, Q, R, S, and T, if P must precede Q and R must follow S, which of the following is a possible order?

Options:

  1. P, Q, S, R, T
  2. S, R, P, Q, T
  3. Q, P, S, R, T
  4. R, S, P, Q, T

Correct Answer: P, Q, S, R, T

Solution:

The order P, Q, S, R, T satisfies the conditions that P is before Q and S is before R.

In a project with tasks P, Q, R, S, and T, if P must precede Q and R must follow

Practice Questions

Q1
In a project with tasks P, Q, R, S, and T, if P must precede Q and R must follow S, which of the following is a possible order?
  1. P, Q, S, R, T
  2. S, R, P, Q, T
  3. Q, P, S, R, T
  4. R, S, P, Q, T

Questions & Step-by-Step Solutions

In a project with tasks P, Q, R, S, and T, if P must precede Q and R must follow S, which of the following is a possible order?
  • Step 1: Identify the tasks involved in the project: P, Q, R, S, and T.
  • Step 2: Understand the conditions: P must come before Q, and S must come before R.
  • Step 3: Start with task P since it must be before Q.
  • Step 4: Place task Q after P because P must precede Q.
  • Step 5: Next, consider task S, which must come before R.
  • Step 6: Place task S before R in the order.
  • Step 7: Finally, add task T, which can be placed anywhere since there are no restrictions on it.
  • Step 8: Combine the tasks in an order that satisfies the conditions: P, Q, S, R, T.
  • Task Precedence – Understanding the order in which tasks must be completed based on given constraints.
  • Logical Reasoning – Applying logical reasoning to determine valid sequences of tasks based on precedence rules.
Soulshift Feedback ×

On a scale of 0–10, how likely are you to recommend The Soulshift Academy?

Not likely Very likely
Home Practice Performance eBooks